Realistic phase-by-phase schedule for residential construction in Pakistan. Plot-size variations, what slows things down, how to plan.
| Plot | Grey Structure | Turnkey | With Basement |
|---|---|---|---|
| 3 Marla | 4-6 months | 7-10 months | +2 months |
| 5 Marla | 4-7 months | 8-12 months | +2 months |
| 7 Marla | 5-7 months | 9-14 months | +2-3 months |
| 10 Marla | 6-8 months | 10-14 months | +2-3 months |
| 1 Kanal | 7-10 months | 12-18 months | +3-4 months |
| 2 Kanal | 10-14 months | 18-24 months | +4-6 months |
Plus 2-6 months upfront for design + approval phase. Plus 1-3 months handover/touch-ups at end.
September-October — gives full dry cycle (Oct-May) for structural work. Avoid June-Aug start due to monsoon disruption.
Mostly: scope creep (owner changes), payment delays, optimistic initial estimates, weather. Realistic estimates + locked scope = on-time delivery.
Possible — finish only ground floor (kitchen + 1-2 bedrooms), move in, complete first floor over next 3-6 months. Saves rent, slightly more total cost.