House Construction Timeline in Pakistan 2026

Realistic phase-by-phase schedule for residential construction in Pakistan. Plot-size variations, what slows things down, how to plan.

By Baqir Ali, CEO Sunshine Contractors

Total Construction Timeline by Plot Size

PlotGrey StructureTurnkeyWith Basement
3 Marla4-6 months7-10 months+2 months
5 Marla4-7 months8-12 months+2 months
7 Marla5-7 months9-14 months+2-3 months
10 Marla6-8 months10-14 months+2-3 months
1 Kanal7-10 months12-18 months+3-4 months
2 Kanal10-14 months18-24 months+4-6 months

Plus 2-6 months upfront for design + approval phase. Plus 1-3 months handover/touch-ups at end.

Phase-by-Phase: 10 Marla Standard Turnkey

Phase 1: Design + Approvals

Duration: 2-4 months (before construction)
  • Architect design (4-8 weeks)
  • Structural engineering (2-3 weeks parallel)
  • MEP design (2-3 weeks parallel)
  • LDA/DHA approval submission (4-8 weeks review)
  • Owner reviews + revisions throughout

Phase 2: Site Preparation + Foundation

Duration: 4-6 weeks
  • Site clearance + leveling (1 week)
  • Excavation (1-2 weeks)
  • PCC + steel reinforcement of footings (1 week)
  • RCC footings + column starters (2 weeks)
  • Backfilling + curing (1 week)

Phase 3: Ground Floor Structure

Duration: 6-8 weeks
  • Plinth beam + slab (2 weeks)
  • Ground floor columns (1-2 weeks)
  • Brickwork ground (2-3 weeks)
  • Slab shuttering + steel (1-2 weeks)
  • RCC slab pour + curing (1-2 weeks)

Phase 4: First Floor + Roof

Duration: 6-8 weeks
  • First floor columns (1-2 weeks)
  • Brickwork first floor (2-3 weeks)
  • Roof slab shuttering + steel (1-2 weeks)
  • Roof RCC pour + curing (1-2 weeks)
  • Parapet + mumty (1 week)

Phase 5: MEP Rough-In + Plaster

Duration: 4-6 weeks
  • Electrical conduit + wiring rough-in (2 weeks)
  • Plumbing pipes rough-in (1-2 weeks)
  • External plaster (2-3 weeks)
  • Internal plaster + curing (2-3 weeks)

Phase 6: Finishing — Floor + Walls

Duration: 6-10 weeks
  • Floor tiles laying (3-4 weeks)
  • Wall tiles in bathrooms + kitchen (2-3 weeks)
  • Wood doors + windows installation (2-3 weeks)
  • Ceiling work (false ceiling, cornice) (2-3 weeks)
  • Wall paint preparation + paint (2-3 weeks)

Phase 7: Kitchen + Bathrooms + MEP Final

Duration: 4-6 weeks
  • Kitchen cabinets + counters (2-3 weeks)
  • Bathroom sanitary + fixtures (2 weeks)
  • Electrical fixtures + switches (1-2 weeks)
  • Built-in wardrobes (2-3 weeks)

Phase 8: External + Boundary + Final Touch

Duration: 3-5 weeks
  • External cladding (Falcon stone) (2-3 weeks)
  • Boundary wall + gate (1-2 weeks)
  • Basic landscape + lawn (1-2 weeks)
  • Utility connections (electricity, gas, water) (1-2 weeks)
  • Final cleaning + touch-ups (1 week)

What Slows Construction Down

How to Keep Construction on Schedule

FAQs

When's the best time to start construction in Pakistan?

September-October — gives full dry cycle (Oct-May) for structural work. Avoid June-Aug start due to monsoon disruption.

Why do projects always run late?

Mostly: scope creep (owner changes), payment delays, optimistic initial estimates, weather. Realistic estimates + locked scope = on-time delivery.

Can I move in earlier than turnkey schedule?

Possible — finish only ground floor (kitchen + 1-2 bedrooms), move in, complete first floor over next 3-6 months. Saves rent, slightly more total cost.