Turnkey Construction Cost in Pakistan 2026

Complete guide to move-in-ready turnkey construction. Plot-size pricing, quality tiers, what's included, city-wise rates + what to expect.

Get Turnkey Quote

What Is Turnkey Construction?

Turnkey construction (also called "complete construction" or "ready-to-move") is a contract where the contractor delivers a fully finished move-in-ready house. Everything from foundation through tiles, paint, fixtures, kitchen, bathrooms is included.

You hand over the plot + design + budget, and receive keys to a move-in house. Single contractor accountable for total quality, schedule, and cost.

What's Included in Turnkey

Standard Turnkey Includes:

Typically Excluded (unless specified):

Quality Tier Comparison

TierMaterialsPremium vs Standard
EconomyLocal tier-2 tiles (Karam), Adam Jee sanitary, single-coat paint, MDF doors-30 to -40%
StandardMaster/Sonex tiles, Master sanitary, plastic emulsion paint, ash doorsBaseline
PremiumImported tiles, Toto/Kohler sanitary, weathershield paint, solid wood doors+30 to +50%
LuxuryItalian marble, designer sanitary (Hansgrohe, Duravit), decorative finishes, oak/teak doors+80 to +150%
Ultra-LuxuryCarrara/Calacatta marble, Bang & Olufsen integration, smart home, premium imports+150 to +300%

Turnkey Cost by Plot Size 2026

PlotEconomyStandardPremiumLuxury
3 MarlaRs 55-75 LacRs 80 Lac-1 CrRs 1-1.3 Cr
5 MarlaRs 70-95 LacRs 95 Lac-1.35 CrRs 1.4-2 CrRs 2-3 Cr
7 MarlaRs 1-1.3 CrRs 1.3-1.9 CrRs 2-2.8 CrRs 3-4 Cr
10 MarlaRs 1.5-1.9 CrRs 1.9-2.8 CrRs 3-4 CrRs 4-6 Cr
1 KanalRs 2.8-3.5 CrRs 3.5-4.5 CrRs 4.5-6.5 CrRs 7-12 Cr
2 KanalRs 6-8 CrRs 8-10 CrRs 10-14 CrRs 15-30 Cr
Reference rate: Lahore, double-story standard. Add 10-15% for Islamabad/Karachi, subtract 8-12% for Multan/Faisalabad.

City-Wise Turnkey Rates 2026

CityStandard Turnkey/sqftPremium Turnkey/sqft
LahoreRs 5,500-6,500Rs 7,500-9,500
IslamabadRs 6,000-7,200Rs 8,500-11,000
RawalpindiRs 5,500-6,500Rs 7,500-9,500
KarachiRs 6,000-7,500Rs 8,500-11,500
FaisalabadRs 4,800-5,800Rs 6,500-8,200
MultanRs 4,500-5,500Rs 6,200-7,800
PeshawarRs 5,500-6,800Rs 7,500-9,800

Turnkey Cost Breakdown

Category% of Turnkey10 Marla Standard (Rs 2.3 Cr)
Grey Structure50-55%Rs 1.15-1.27 Cr
Floor + wall tiles10-13%Rs 23-30 Lac
Paint + plaster finishing4-6%Rs 9-14 Lac
Doors + windows6-8%Rs 14-18 Lac
Kitchen + bathrooms10-12%Rs 23-28 Lac
Electrical fixtures4-6%Rs 9-14 Lac
External works4-6%Rs 9-14 Lac
Contractor fee3-5%Rs 7-11 Lac

Turnkey Build Timeline

FAQs — Turnkey Cost

Is turnkey worth the premium over grey?

For time-poor owners — yes. Single contractor accountable, predictable schedule, no material headaches. For hands-on owners — grey may save 10-15%.

Can I upgrade materials in turnkey?

Yes — owner-specified premium materials common. Upgrade cost charged separately on actual + markup. Specify clearly in contract.

What's not included in standard turnkey?

Pool, smart home, premium imported materials, designer landscape, custom furniture, solar (unless specified). Common add-ons billed separately.

Turnkey vs hiring separate finisher?

Turnkey single contractor accountable for total quality. Separate finisher coordination falls on owner — typically 5-15% extra in cost overruns + delays.